Another consideration when it comes to creating estimates is Parkinson's Law. Parkinson's Law states that work will expand to fill the amount of time it is allotted. Here's an example: you, the project manager, are working with your project team to determine how long each activity will take to complete. Suzie knows that an assignment she'll be completing for the project will probably take 32 hours to complete. Suzie, however, knows that there might be some problems, some snags, or some other delay, so she "pads" the duration estimate by eight hours and tells you it'll likely take her 40 hours to complete the assignment.
Guess what? It'll magically take 40 hours to complete the work. Suzie will either complete the work in 32 hours and not tell you she's done because she reported it'll take 40 hours or she'll ease through the work and use all 40 hours to complete the 32-hour assignment. Another possibility is that Suzie won't start on the actual work until hour eight and she'll pray and hope nothing goes awry in the assignment. The worst possible scenario is that she'll wait until hour eight to begin, things do go awry, and she'll require more than the allotted 40 hours for the work.
There are multiple strategies to combat Parkinson's Law, one of which is the three-point estimate. Another approach is to use a "management reserve" which is a pool of time that all activities may borrow from should their activities go over the allotted completion time. In other words, if a project is estimated to take ten months to complete the project manager will allot approximately 15% additional time for management reserve. The project will, in this instance, take eleven and a half months to complete. As activities are late the time is subtracted from the management reserve. To use management reserve, however, the project manager and the project team must agree to be accurate and as honest as possible when estimating how long activities may take to complete.
Recent Comments